New Data Center and Operations Control Center
Confidential Client | Jackson, MS
PROJECT DATA:
CONSTRUCTION COST: $18.9 Million
SIZE: 23,000 SF
In Association with RTKL
SUMMARY:
Dale Partners provided design services for this new mission critical data center for a confidential client. The project consisted of programming and long range planning for 15-year growth. The building was designed to remain in operation should there be a complete utility outage and is hardened to withstand the wind pressures of an F3 tornado. The data center was designed as a Tier II Classification with Level 5 Commissioning. The project also includes a new Operations Command Center.